|
Contract Law Page |
| DISCHARGE OF CONTRACT |
|
A contract may be discharged by performance, agreement, breach, or
frustration. 1. PERFORMANCE
THE GENERAL RULE The general rule is that the parties must perform precisely all the terms of the contract in order to discharge their obligations. For example, in contracts for the sale of goods, s13 Sale of Goods Act 1979 imposes the condition that the goods must correspond with the description. The precise requirement of s13 was illustrated in:
The classic example of hardship caused by this rule is the case of:
MODIFICATION OF THE GENERAL RULE The strict rule as to performance is mitigated in a number of instances: A) DIVISIBLE CONTRACTS A contract may be entire or divisible. An entire contract is one where the agreement provides that complete performance by one party is a condition precedent to contractual liability on the part of the other party. With a divisible contract, part of the consideration of one party is set off against part of the performance of the other. Contrast:
B) ACCEPTANCE OF PARTIAL PERFORMANCE Where the party to whom the promise of performance was made receives the benefit of partial performance of the promise under such circumstances that he is able to accept or reject the work and he accepts the work, then the promisee is obliged to pay a reasonable price for the benefit received. But it must be possible to infer from the circumstances a fresh agreement by the parties that payment shall be made for the goods or services in fact supplied. See:
C) COMPLETION OF PERFORMANCE PREVENTED BY THE PROMISEE Where a party to an entire contract is prevented by the promisee from performing all his obligations, then he can recover a reasonable price for what he has in fact done on a quantum meruit basis in an action in quasi-contract. See:
D) SUBSTANTIAL PERFORMANCE When a person fully performs the contract, but subject to such minor defects that he can be said to have substantially performed his promise, it is regarded as far more just to allow him to recover the contract price reduced by the extent to which his breach of contract lessened the value of what was done, than to leave him with no right of recovery at all. Contrast:
E) TENDER OF PERFORMANCE Tender of performance is equivalent to performance in the situation where party (a) cannot complete performance without the assistance of party (b) and party (a) makes an offer to perform which party (b) refuses. See:
STIPULATIONS AS TO TIME OF PERFORMANCE At common law, in the absence of contrary intention, time was regarded as being of the essence. Thus if a party did not perform on time he could not enforce the contract against the other party. Section 41 Law of Property Act 1925 modified this common law rule by providing that the equitable principle shall prevail with the result that if time is not of the essence, a right to damages accrues but not a right to terminate the contract. In equity time was not regarded as being of the essence, except in three circumstances:
2. AGREEMENT
The general rule is that what has been created by agreement may be extinguished by agreement. An agreement by the parties to an existing contract to extinguish the rights and obligations that have been created is itself a binding contract, provided that it is made under seal or supported by consideration. Where the agreement for discharge is not under seal, the legal position varies according to whether the discharge is bilateral or unilateral:
BILATERAL DISCHARGE Bilateral discharge occurs whenever both parties to the contract have some right to surrender, eg where there has been non-performance by either party, or is partly performed by one or both parties. The agreement by the parties to discharge their contract may be designed to have one of several effects: (A) ACCORD AND SATISFACTION (B) RESCISSION AND SUBSTITUTION (C) VARIATION (D) WAIVER UNILATERAL DISCHARGE Unilateral discharge takes place where only one party has rights to surrender. Where one party has entirely performed his part of the agreement, he is no longer under obligations but has rights to compel the performance of the agreement by the other party. For unilateral discharge, unless the agreement is under seal, consideration
must be furnished in order to make the agreement enforceable, ie accord and
satisfaction. 3. BREACH
A failure to perform the terms of a contract constitutes a breach. A breach which is serious enough to give the innocent party this option of treating the contract as discharged can occur in one of two ways:
One preliminary question, in cases of anticipatory breach, is to ascertain whether, once repudiation has been communicated to the innocent party, that party accepts the repudiation or not. The question of whether silence/inaction can amount to acceptance of repudiation was considered in:
The innocent party is not under any obligation to wait until the date fixed for performance before commencing his action, but may immediately treat the contract as at an end and sue for damages. See:
If within a reasonable time the innocent party does not indicate that he accepts the other party's repudiation so that the contract is discharged, then the contract remains open for the benefit of, and the risk of, both parties. The breach was not accepted in:
It appears that the right to keep the contract alive subsists even where the innocent party is increasing the amount, and not mitigating, the damages which he may receive from the party in breach. See:
Where the innocent party elects to treat the contract as continuing (ie, he affirms it) the affirmation can be regarded as a species of waiver. The innocent party waives his right to treat the contract as repudiated and may be estopped from changing his election. See:
If the innocent party elects to affirm a contract after an anticipatory breach by the other party, he is not absolved from tendering further performance of his own obligations under the contract. Consequently, the repudiating party could escape liability if the affirming party was subsequently in breach of the contract. See:
Whether the anticipatory breach amounts to a repudiation depends on the actual circumstances of the case. Lord Selborne stated in Mersey Steel v Naylor Benzon (1884) 9 App Cas 434:
The difficulty that can arise in determining whether the conduct amounts to a repudiation is illustrated by a comparison of two decisions in the House of Lords:
4. FRUSTRATION
The doctrine of frustration operates in situations where it is established that due to subsequent change in circumstances, the contract is rendered impossible to perform, or it has become deprived of its commercial purpose by an event not due to the act or default of either party. Frustration is not to be confused with initial impossibility, which may
render the contract void ab initio. See Couturier v Hastie (1856) 5 HL Cas 673
(Handout on Mistake). TESTS FOR FRUSTRATION There are two alternative tests for frustration: (1) The implied term theory, as in:
Lord Loreburn explained in FA Tamplin v Anglo-Mexican Petroleum [1916] 2 AC 397, that the court:
(2) The radical change in the obligation test. This was adopted by the majority of the House of Lords in:
In National Carriers v Panalpina [1981] AC 675, Lord Wilberforce was
reluctant to choose between the theories. He took the view that they merged one
into the other and that the choice depends upon "what is most appropriate
to the particular contract under consideration". EXAMPLES OF FRUSTRATION A) DESTRUCTION OF THE SPECIFIC OBJECT The destruction of the specific object essential for performance of the contract will frustrate it. See:
B) PERSONAL INCAPACITY Personal incapacity where the personality of one of the parties is significant may frustrate the contract:
C) THE NON-OCCURENCE OF A SPECIFIED EVENT The non-occurence of a specified event may frustrate the contract. Compare the leading cases:
D) INTERFERENCE BY THE GOVERNMENT Interference by the government may frustrate a contract. See:
E) SUPERVENING ILLEGALITY A contract may become frustrated if it later becomes illegal. See:
F) DELAY Inordinate and unexpected delay may frustrate a contract. The problem is to know how long a party must wait before the delay can be said to be frustrating. See:
LIMITATIONS OF THE DOCTRINE · 'The doctrine of frustration must be applied within very narrow limits',
per Viscount Simmonds in Tsakiroglou [1961] (below). A) EXPRESS PROVISION FOR FRUSTRATION The doctrine of frustration cannot override express contractual provision for the frustrating event.
The mere increase in expense or loss of profit is not a ground for frustration. See:
See:
D) FORESEEABILITY OF THE FRUSTRATING EVENT A party cannot rely on an event which was, or should have been, foreseen by him but not by the other party. See:
EFFECTS OF FRUSTRATION The Law Reform (Frustrated Contracts) Act 1943 was passed to provide for a
just apportionment of losses where a contract is discharged by frustration. (For
the previous inflexible common law rules see ILEx Textbook, 13.5.4) (A) RECOVERY OF MONEY PAID Section 1(2) provides three rules:
For an example, see:
(B) VALUABLE BENEFIT Section 1(3) provides:
A case has discussed, inter alia, the meaning of the words 'valuable benefit'. See:
(C) SCOPE OF THE 1943 ACT Section 2(3) permits contracting out. Section 2(4) provides that the Act does not apply where wholly performed contractual obligations can be severed from those affected by the frustrating event. Section 2(5) provides that the Act does not apply to:
|
|
|
| Home | About | Search | Links | Message Boards | Revision Guides | Photos | Contact |